Engineering hub
Engineering Hub: System Design, Drawings & BOQ
Enter the duty, or describe any requirement and attach the drawing. AutoCAD, PDF, a spreadsheet or a photograph is accepted. The desk sizes what it can from NBC 2016 Part 4, IS 15105, IS 3844, IS 13039, TAC, NFPA 13, NFPA 20, IS 732, IS 3043, IS 2189, ISHRAE and ASHRAE 62.1, draws the P&ID or single-line diagram, the scaled plan, both elevations, section A-A and the isometric, and writes the bill. A PEB shed takes length, width, eave, bay, slope, basic wind speed, crane and cladding, and draws the framing plan, the anchor bolt plan, both elevations, section A-A and a rotatable 3D model. Fire suppression and fire detection sit under Fire protection, not as a separate project type. A mark you add on the sheet is saved with the download. A licensed engineer still stamps the issue.
Choose project type
ETP is selected. The subcategories for this type are under this list. The drawing and the bill further down are the existing type page. A catalogue price is used when it matches. Otherwise a published Indian rate plus 20% is shown with its source. Erection is 10% of that system's materials, testing 2%, and transport 3%.
Subcategories
Each subcategory has its own design basis, calculation, drawings, bill and quotation.
Drawing is listening

Rev A
SHEET 1 OF 6
Calculation
| Part | Formula | Working | Result | Standard |
|---|---|---|---|---|
| Hydraulic load | m³/h = KLD / operating hours | 200 m³/day / 20 h | 10.0 m³/h | CPCB / GPCB consent |
| Clarifier | The larger of detention volume and SOR area × side-water depth | SOR 0.8 m/h needs 12.5 m², which is 37.5 m³ at 3 m side-water depth. Detention 2.5 h needs 25.0 m³. The clarifier is the next standard size at or above 37.5 m³. | 37.5 m³ required; 50 m³ standard size selected | CPCB manual |
Design basis
| Part | Specification | Standard |
|---|---|---|
| clarifier 50 | 200 KLD, 10 m³/h. 37.5 m³ required; 50 m³ standard size selected. | CPCB |
| tube settler 10 | Lamella ahead of the clarifier. | CPCB |
| filter press 630 | Sludge dewatering. | Process datasheet |
| RO 5000 | Polishing RO. Recovery is on the offer. | Process datasheet |
| PAC 25 | Coagulant, 25 kg packs. | COA |
| dosing skid | One skid for coagulant and one for polymer. | Process datasheet |
| ETP pipe | Interconnecting pipe, 50 NB, 400 m, from 200 KLD. The catalogue figure is a per-metre rate. | IS 1239 |
| Elbow | Elbows on the interconnecting pipe. | ASME B16.9 |
| Tee | Branch tees. A reducer is not added when both ends are 50 NB. | ASME B16.9 |
| Coupling | Screwed couplings on the dosing and drain lines. A 25 NB union is not put on this 50 NB line. | ASME B16.11 |
| Valve | Isolation at each tank nozzle. | API 600 |
| Check valve | Non-return on the transfer pump and the filter feed. | API 594 |
| Strainer | One strainer ahead of the pump and one ahead of the RO. | Site practice |
| Flange | Two flanges on each isolation valve. | ASME B16.5 |
| Gasket | One gasket on each flange. | ASME B16.20 |
| Bolt | Eight bolts on each valve. Calc 160 bolts | Billed 2 lots of 100. M16 × 60 mm, grade 8.8. The catalogue price is a box or lot, so it is not multiplied by the bolt count. | ISO 4014 |
| Hanger | 400 m of ETP pipe. One hanger about every 3 m, 134 clamps, 50 mm to match the line. Price on request unless the catalogue has this bore. An 80 mm clamp is not used on a different line. | Site practice |
| Transfer pump | Transfer pump. Plant flow is 10 m³/h. Next catalogue pump at or above that flow is 10 m³/h at 15 m, an allowance for a short transfer, not a fire pump. | ISO 5199 |
| Pressure gauge | Pump discharge and filter inlet. 4 inch dial, 0–10 kg/cm². | IS 3624 |
| Level switch | One tank float switch on the collection tank. | Process datasheet |
| Flow switch | One 100 mm vane flow switch on the treated outlet. | Process datasheet |
| Primer | 400 m of 50 NB interconnecting pipe. About 63 m². Two coats, an allowance of 10 m² per litre per coat. | IS 1477 |
| Finish paint | 400 m of 50 NB interconnecting pipe. One finish coat on the same area. Asian Paints Apcolite gloss, the published 1 L rate. | IS 1477 |
| Welding rod | Fillet allowance on the flanged joints. | AWS A5.1 |
| Testing | ETP testing and commissioning. 2% of this system's material subtotal, ex-GST. GST 18% is added on this allowance. | Site practice |
| Erection | ETP erection and installation labour. 10% of this system's material subtotal, ex-GST. GST 18% is added on this allowance. | Site practice |
| Transport | ETP transport and freight. 3% of this system's material subtotal, ex-GST. GST 18% is added on this allowance. | Site practice |
ETP BOQ
Proactive Industrial Private LimitedGSTIN: 24AAQCP1475R1ZLRegistered office: C-119, Siddhivinayak Business Tower, Makarba, Sarkhej, Ahmedabad, Gujarat 380051Branch offices: Vadodara | Padal (Kheda) | BharuchSupply
clarifier 50
200 KLD, 10 m³/h. 37.5 m³ required; 50 m³ standard size selected. · CPCB
1 no. × —
GST —
Amount —
tube settler 10
Lamella ahead of the clarifier. · CPCB
1 no. × —
GST —
Amount —
filter press 630
Sludge dewatering. · Process datasheet
1 no. × —
GST —
Amount —
RO 5000
Polishing RO. Recovery is on the offer. · Process datasheet
1 plant × —
GST —
Amount —
PAC 25
Coagulant, 25 kg packs. · COA
20 pack × —
GST —
Amount —
dosing skid
One skid for coagulant and one for polymer. · Process datasheet
2 no. × —
GST —
Amount —
GI pipe 50 NB heavy
Interconnecting pipe, 50 NB, 400 m, from 200 KLD. The catalogue figure is a per-metre rate. · IS 1239
400 m × —
GST —
Amount —
90 elbow 50 NB Sch 40
Elbows on the interconnecting pipe. · ASME B16.9
20 no. × —
GST —
Amount —
equal tee 50 NB Sch 40
Branch tees. A reducer is not added when both ends are 50 NB. · ASME B16.9
10 no. × —
GST —
Amount —
forged coupling 50 NB
Screwed couplings on the dosing and drain lines. A 25 NB union is not put on this 50 NB line. · ASME B16.11
34 no. × —
GST —
Amount —
gate valve 50 NB
Isolation at each tank nozzle. · API 600
20 no. × —
GST —
Amount —
check valve 50 NB
Non-return on the transfer pump and the filter feed. · API 594
2 no. × —
GST —
Amount —
Y strainer 50 NB
One strainer ahead of the pump and one ahead of the RO. · Site practice
2 no. × —
GST —
Amount —
flange 50 NB class 150 A105
Two flanges on each isolation valve. · ASME B16.5
40 no. × —
GST —
Amount —
spiral wound gasket 50 NB class 150
One gasket on each flange. · ASME B16.20
40 no. × —
GST —
Amount —
hex bolt M16 60 mm grade 8.8
Eight bolts on each valve. Calc 160 bolts | Billed 2 lots of 100. M16 × 60 mm, grade 8.8. The catalogue price is a box or lot, so it is not multiplied by the bolt count. · ISO 4014
2 lot × —
GST —
Amount —
GI pipe clamp 50 mm
400 m of ETP pipe. One hanger about every 3 m, 134 clamps, 50 mm to match the line. Price on request unless the catalogue has this bore. An 80 mm clamp is not used on a different line. · Site practice
134 no. × —
GST —
Amount —
centrifugal pump 10 m3/h 15 m
Transfer pump. Plant flow is 10 m³/h. Next catalogue pump at or above that flow is 10 m³/h at 15 m, an allowance for a short transfer, not a fire pump. · ISO 5199
1 no. × —
GST —
Amount —
pressure gauge
Pump discharge and filter inlet. 4 inch dial, 0–10 kg/cm². · IS 3624
2 no. × —
GST —
Amount —
level switch
One tank float switch on the collection tank. · Process datasheet
1 no. × —
GST —
Amount —
flow switch
One 100 mm vane flow switch on the treated outlet. · Process datasheet
1 no. × —
GST —
Amount —
red oxide metal primer 1 L
400 m of 50 NB interconnecting pipe. About 63 m². Two coats, an allowance of 10 m² per litre per coat. · IS 1477
13 L × —
GST —
Amount —
synthetic enamel finish 1 L
400 m of 50 NB interconnecting pipe. One finish coat on the same area. Asian Paints Apcolite gloss, the published 1 L rate. · IS 1477
7 L × —
GST —
Amount —
welding electrode E6013 3.15 mm
Fillet allowance on the flanged joints. · AWS A5.1
5 kg × —
GST —
Amount —
transport to site
ETP transport and freight. 3% of this system's material subtotal, ex-GST. GST 18% is added on this allowance. · Site practice
1 lot × —
GST —
Amount —
Supply subtotal—
Installation
testing and commissioning
ETP testing and commissioning. 2% of this system's material subtotal, ex-GST. GST 18% is added on this allowance. · Site practice
1 lot × —
GST —
Amount —
erection and labour
ETP erection and installation labour. 10% of this system's material subtotal, ex-GST. GST 18% is added on this allowance. · Site practice
1 lot × —
GST —
Amount —
Installation subtotal—
GST —
Grand total —
Supply is the material and the transport. Installation is erection, testing and commissioning, and the other site services. Each section has its own ex-GST subtotal. GST and the grand total follow. A catalogue match is used when the catalogue has a price. Where it does not, the rate is a published Indian marketplace or maker price plus 20%, and the source is on the line. Every material rate is ex-GST, and GST at 18% is added on it. A published price that already included GST is converted to the ex-GST figure and 18% is shown separately. Erection and installation labour is 10% of that system's material subtotal, testing and commissioning 2%, and transport 3%, with GST at 18% on those allowances.
Freight
Ahmedabad to Vadodara · about 131 km · chargeable 150 kg
Freight ₹1,800 ex-GST · GST ₹324 · Payable ₹2,124
Road part-load from the pincode. Chargeable weight is the higher of actual kg and 300 kg per cubic metre. Confirm the truck before a PO.
- 2,000 m² is the area of one floor, 2 floors, 8 m height. Sprinkler heads, sprinkler branch pipe and smoke detectors are that floor counted again on every floor. The sprinkler pump stays on the remote design area.
- Prices on the quotation are ex-GST. A catalogue match is used first. Where the catalogue has no price, a published Indian rate plus 20% is used and the source is on the line. GST at 18% is added on every material line. A price the source already quoted including GST is converted to the ex-GST rate and 18% is shown separately. Erection and installation labour is 10% of that system's material subtotal, testing and commissioning 2%, and transport 3%. GST 18% is added on those allowances.
- Standards cited on this desk: NBC 2016 Part 4, IS 15105, IS 3844, IS 13039, TAC, NFPA 13, NFPA 20, IS 732, IS 3043, IS 2189, ISHRAE and ASHRAE 62.1.
- Effluent design flow is 200 KLD, which is 200 m³/day, at 10 m³/h over 20 hours. The clarifier is the next standard size, 50 m³.
Get this designed & installed by us
Statutory
- This is an enquiry BOQ, not a sanctioned design. A licensed consultant stamps the drawing before construction.
- Consent to Establish and Consent to Operate from the State Pollution Control Board. In Gujarat that is GPCB. Hazardous sludge needs authorisation under the Hazardous and Other Wastes Rules. The consent limits replace this allowance.